Scope of works:
- Construction of the basic 15kV PKP1 feeder line.
- Construction of back-up 15kV PKP2 feeder line.
- Housingfor 9-bay,two-section switchgear SN 15kV AC.
- Housing for switchgear 3kV DC.
- Housing for two sets of rectifiers, input voltage of 15kV. Installation of the cell (-)and electronic ground fault protection device.
- Housing for switchgear 230/400 V AC.
- Housing for switchgear 220 V DC.
- Housing for the set of batteries, charging rectifier, and inverter.
- Construction of feeder cable line.
- Construction of return cables.
- Installation of feeder subordinations.
- Construction of the lines and devices for local and remote control with feeder cable disconnecting switch.
- Construction of the new traction substation building with LV installations and necessary infrastructures.
Status of the project:
Completed
Client:
PKP Energetyka S.A.
Implementation period:
06.06.2019 – 15.07.2020