Construction of double-circuit overhead line 400 kV Kromolice-Pątnów following the route of the 220 kV line Plewiska-Konin

Scope of works:
  • Design engineering.
  • Formal and legal matters.
  • Disassembly of the existing 220 kV line Plewiska-Konin.
  • Construction of double-circuit overhead 400 kV line.
  • Inspection of the line with thermovision method and KORONA method.
Status of the project: Completed
Client: PSE S.A.
Implementation period: 2009 - 2012