Scope of works:
  1. Formal and legal matters, obtaining permits and approvals.
  2. Construction and start-up of PT Widełka, along with land development works.
  3. Construction and start-up of RS BudyGłogowskie, along with land development works.
  4. Construction and start-up of feeder, return, and control cables, as well as fibre optic tract.
  5. Construction and start-up of water supply connection to PT Widełka.
  6. Construction and start-up of input 110kV line to RS BudyGłogowskieand construction of connection from RS BudyGłogowskieto PT Widełka.
  7. Construction and start-up of telecom/telecontrol system at the facility, and executing the subordinations between the neighbouring substations, i.e., PT Rzeszów (substation design under construction) and PT Cmolas.
Status of the project: Completed
Client: PKP Energetyka S.A.
Implementation period:

13.10.2020 – 27.05.2021