Formal and legal matters, obtaining permits and approvals.
Construction and start-up of PT Widełka, along with land development works.
Construction and start-up of RS BudyGłogowskie, along with land development works.
Construction and start-up of feeder, return, and control cables, as well as fibre optic tract.
Construction and start-up of water supply connection to PT Widełka.
Construction and start-up of input 110kV line to RS BudyGłogowskieand construction of connection from RS BudyGłogowskieto PT Widełka.
Construction and start-up of telecom/telecontrol system at the facility, and executing the subordinations between the neighbouring substations, i.e., PT Rzeszów (substation design under construction) and PT Cmolas.
Construction of 110 kV power line NowyŻmigród-Iwonicz in the frames of the project"Construction of 110 kV line NowyŻmigród-Iwoniczto enable advancement of renewable energy services in the southern part of the Podkarpackie Region”
Scope of works:
Construction of 118 cast/pile foundations.
Construction of 118 pylon structures.
Construction of 25.278 km phase conductors andOPGW.
Construction of two sections of 110kV earth cables.